The Duluth Airport Authority (DAA) has completed another construction season at DLH. This year’s projects included phase 6 of the Taxiway A reconstruction project and the reconstruction of a portion of the Midfield Ramp.
These projects mark another significant step in the ongoing modernization of Duluth International
Airport’s airfield infrastructure.
This $12.5 million airfield construction season began in May and wrapped up in early November, advancing critical improvements to the airport’s taxiway system whilemaintaining operations throughout the busy summer travel season. Despite variable weather conditions and the logistical demands of working on an active airfield, construction remained on schedule.
Phase 6 of the Taxiway Alpha project involved extensive excavation, with crews removing more than 135,000 cubic yards of organic material before installing approximately 12,500 cubic yards of new concrete pavement. The project also included installation of more than 15 miles of electrical cable to support upgraded taxiway lighting and navigational systems.
Beyond the improvements to airport infrastructure, the project also generated economic activity throughout the region. At least nine contractors and 95 individual employees contributed to the work. Employees traveling to Duluth for the project supported the local economy through overnight stays at area hotels, dining at local restaurants and patronizing other regional businesses.
These additional benefits demonstrate how airport infrastructure investments can extend beyond the airfield and positively impact the surrounding community.
“Projects like this are about more than replacing pavement. They’re about making long- term investments in the infrastructure that keeps our airport operating safely,” said Tom Werner, Executive Director of the Duluth Airport Authority. “Completing another phase of Taxiway A brings us one step closer to a modernized airfield that can support the evolving needs of aviation and our region for years to come.”
The DAA recognizes the many partners who contributed to the successful completion of Phase 6, including Schafer Construction as the prime contractor and Short Elliott Hendrickson Inc. for engineering and design services. The coordination, expertise and commitment of these teams were essential in delivering this complex project while minimizing impacts to ongoing airport operations.
About the Duluth International Airport
Beginning Jan. 29, 2026, Sun Country Airlines resumed nonstop service between Duluth International Airport (DLH) and Fort Myers, Florida (RSW). Year-round service also includes daily nonstop flights to Chicago (ORD) on United Airlines and Minneapolis (MSP) on Delta Air Lines.
The Duluth Airport Authority is committed to providing travelers with a safe, secure, and welcoming airport experience. Travelers are also invited to enjoy Club DLH Business Suite, designed with the working traveler in mind. For flight information, airport amenities and more, visit duluthairport.com or follow us on Facebook at facebook.com/duluthairport.